
First blast furnace blown-in 1911
» The Beginning
» The War Years
» Expansion to Two Million Tonnes
» Period between 1960-80
» Steelmaking and casting
» Tata Steel Today |
Expansion
to Two Million Tonnes
The Steel target of six million tonnes of ingot Steel per
annum in India set for the second five year plan included
expansion of the existing Steel plants. Tata Steel was permitted
to go in for an expansion to two million tonnes of ingot Steel
per annum. Tata Steel’s expansion programme, the largest
project in the private sector, was started in 1955 and completed
by December 1958.
The rated daily capacity of the five blast furnaces in existence
prior to TMP was 4200 tonnes. Blast furnace F, with a rated
capacity of 1650 tonnes per day, provided sufficient hot metal
for the two million tonne programme.
By providing sintered ore, blast furnace production increased
by 10% to an annual output of 1,870,000 tonnes. Blast furnace
F was completed and put in operation on October 10, 1958.
One of the largest and most modern furnaces in the world,
it was designed for high top-pressure operation and the use
of sinter in the burden. The blowing-in ceremony of blast
furnace F was regarded as the official christening of TMP.
A huge Steel Melting shop no. 3 (closed down in 1999) comprising
two 800 tonne hot metal mixers, three 32 tonne Bessemer converters
and seven 200 tonne open-hearth furnaces (with the possibility
of adding an eighth furnace) was the corner stone of steelmaking
under TMP.
A new rolling mill complex was constructed consisting of
soaking pits, Blooming Mill no.2 and a sheet Bar and Billet
mill (this was closed in early 1999). Between the two mills,
the primary capacity was nearly three million tones of ingots
per annum. The continuous sheet bar and billet mill no.2 was
the main mill for semi-finished products for feeding the sheet
mills, tin bars for the tinplate company and gothics for the
manufacture of seamless tubes.
The Medium and Light Structural mill, which was also installed
along with the other mills, was capable of rolling diversified
products in wide ranges and was designed to roll 350,000 tonnes
of blooms per annum. The products manufactured were to be
mainly beams, channels, angles, junior beams and parallel
flange beams-the last two for the first time in country. The
revamping of the rail and structural mill (closed down in
1989), sheet bar and billet mill no.1 (closed down in 1998)
and the merchant mill were also undertaken. A new merchant
mill no.2 was commissioned in 1962. The additional service
facilities included water supply arrangement, power supply
and distribution to meet the total maximum demand of 125,000
kW and railway track facilities. The two million tonne programme
was completed on schedule and involved no major delay.
|